A vocational training centre named after Joshua Mqabuko Nkomo is being constructed in St Joseph’s, Matobo District, as part of efforts to honour his legacy ahead of Zimbabwe’s 46th Independence Day celebrations, which will be held in Maphisa.
The project forms part of the government’s legacy initiatives, with Phase One scheduled for completion in time for the main celebrations on 18 April.


During a media tour of the site, Engineer Gift Masuku said current works are focused on key infrastructure that will lay the foundation for the institution.
The centre sits on a 22-hectare site and has already recorded significant progress, particularly on perimeter security and internal roads.
“For Phase One, we are constructing the boundary wall and fencing around the vocational training centre. So far, the boundary wall is about 60 to 70 percent complete, while the perimeter fencing has been fully completed,” he said.
Eng Masuku added that construction of the internal road network, spanning approximately eight kilometres, is also advancing, with around 65 percent of the work done.
“The road construction includes several layers, from subgrade up to base levels. Most of the groundwork, including topsoil removal and compaction, has been completed. We are now awaiting final processes such as soil testing before moving to the next phase,” he said.
On structural developments, Eng Masuku said the administration block has reached roughly 40 percent completion.
“The substructure brickwork is about 50 percent complete, while the superstructure brickwork is nearing 30 percent. Some sections have reached ring beam level,” he said.
Progress has also been made on classroom facilities. The first block of eight classrooms is nearing completion.
“The initial eight classrooms are approximately 90 percent complete, with roofing works already under way. The second block of eight classrooms is at foundation stage, with footing excavation around 75 percent complete and concrete pouring ongoing,” he said.
Additional works under Phase One include the construction of a gatehouse and workshops.
Eng Masuku said the steel structure for the gatehouse is between 20 and 40 percent complete and could be finalised within days.
“Workshop construction is still at an early stage, with excavation and column works currently under way, placing progress at about 20 percent. Some workshop materials are being fabricated off-site to speed up erection once the groundwork is complete,” he said.
He added that the next phase of the project will include expanded facilities such as a multipurpose hall, a library, student hostels, staff accommodation, a clinic and a police post.
Support CITE’s fearless, independent journalism. Your donation helps us amplify community voices, fight misinformation, and hold power to account. Help keep the truth alive. Donate today
